Go to: OVERVIEW (SaveOurCounty) DETAILS (listener) PLANNING SCHOOLS ENVIRONMENT EROSION Report corrections & broken links to Webmaster Get updates on local issues
PUBLIC SERVICE
COMMISSION OF WEST VIRGINIA
FINAL MEMORANDUM
DATE: May
29, 2009
TO: Ronald E. Robertson, Staff
Attorney
Legal
Division
FROM: Randy Lengyel, Utilities Analyst III
Water
and Wastewater Division
Jim
Weimer, P.E., Engineer II
Engineering
Division
SUBJECT: CASE NO: 04-0095-S-CN
City
of Charles Town Sewer Department
Application
for a Certificate of Convenience and Necessity to construct improvements to its
existing wastewater treatment system.
(filed
1/26/04).
Initial
Memo.
The
City of Charles Town Sewer Department has filed an application for a
Certificate of Convenience and Necessity
to construct an effluent discharge line to the Shenandoah River. Since the original filing, Staff has been
informed of additional improvements needed to its existing wastewater treatment
system which will become a part of the Certificate filing.
The
City has proposed funding the project with revenue bonds issued by the City and
secured by a large land developer. A
current tariff provision requires that a Capacity Improvement Capital Cost
(CICC) fee be imposed on all new sewer users.
The fee is anticipated to be adopted by the City of Charles Town's
neighboring City of Ranson and the Jefferson County Public Service
District. All are served by the Charles
Town sewage treatment plant. All
entities would be required to collect the fee from all new users connected to
the Charles Town plant. This fee is
anticipated to cover the costs of the bond repayments during the out
years. The most recent project cost
breakdown is as follows:
CONSTRUCTION
COST $1,435,573
ENGINEERING
DESIGN $ 85,200
TECHNICAL
SERVICES $ 157,000
LEGAL
AND FISCAL $ 30,000
SITE
AND EASEMENTS $ 25,000
UNDERWRITERS
DISCOUNT&OID $ 92,387
COST
OF BOND ISSUANCE $ 40,000
FUNDED
RESERVE $ 210,000
PROJECT
CONTINGENCY $ 510,000
TOTAL
EST. PROJECT COST $2,585,200
Staff
notes that the engineering design services were paid previously and are
not part of the amount to be financed in the project funding. The total financed will be $2,500,000.
ENGINEERING
REVIEW
The
City of Charles Town has proposed a project to expand plant capacity due to
significant growth in Jefferson County.
The Charles Town plant treats sewage for the City of Ranson and all
sewage generated by the Jefferson County Public Service District. It is currently
the owner of the only large treatment facility in Jefferson County. The Utility has a collection system
consisting of approximately 25 miles of various sizes of sewer gravity and
force mains. The Utility operates 22
lift stations of varying capacity.
These lines all terminate at the City's Sequencing Batch Reactor (SBR)
plant. The current project will include
the addition of two blowers to an existing SBR blower building, upgrades to the
electrical system, and the addition of a new sludge digester and associated
equipment.
The
documents provided to complete the review were provided with either the
application or in subsequent filings.
These included:
$
The Facility Plan
$
The design drawings
$
The contract documents
$
The final engineering report
$
The Operation and Maintenance cost estimates
The
proposed project provides no new customers as it is related only to necessary
repairs and upgrades to meet current WVDEP discharge requirements and as a
necessary step for a capacity increase.
Plant capacity for the Sequencing Batch Reactor type treatment facility
will likely be permitted to increase to a possible maximum of 1.75 million gallons per day (MGD) from its
current 1.2 MGD limit. The actual
increase has not yet been determined by the WVDEP but will likely be staged as
effluent monitoring verifies compliance with new permit requirements. A WVDEP NPDES permit has not yet been
granted for the plant upgrades but is expected prior to spring 2005.
PERMITS
The
City has been granted a WVBuPH construction permit for the plant additions.
Permit No. 16195 was issued on August 20, 2004. The NPDES permit is expected after a review of the current plan
and presentation before the public. No
other permits are required as all construction will occur within the boundaries
of the existing plant.
OPERATION
AND MAINTENANCE EXPENSES
The
project is expected to increase operating costs by approximately $90,000
annually due primarily to increases in the cost of power for the digester. However, Staff recommends that the O&M
be increased to $104,000 to acknowledge operation of the blowers for the SBR
basins. The cost associated with
operation of the belt press should initially decrease as the sludge loading
from the digester will be less than the current sludge loads from the sludge
holding tanks.
COMPARISON
DATA
The
project proposes no new customers and is to be initially funded with guaranteed
developer contributions anticipating significant future growth. The growth is anticipated to provide the
revenues necessary to support the project in the out years. The funding package also anticipates debt
repayment from Capital Improvement Fees (CIF) which are paid by developers for
each new EDU put in service. (These fees were approved by the Commission for
Berkeley County PSSD in Case No. 04-0153-PSD-PC and were requested by Jefferson
County PSD in Case No. 03-1490-PSD-T-PC).
The total cost of the blower addition is estimated at $500,000 while the
digester is estimated at $1,500,000. A
$500,00 project contingency is proposed which brings total project cost to
$2,500,000.
It
is anticipated that the sludge digester will reduce short term sludge disposal
cost by approximately $3000 per year.
Debt service for the digester will total approximately $118,000 per year
with an additional annual operating cost of approximately $83,000. While the
construction cost is not justified on a cost savings basis, the WVDEP believes
the flexibility provided to a plant operator for sludge level control in the
SBR basins and the resulting protection afforded to the discharge stream during
high flow events justifies the expense.
Sludge conditioning for eventual de-watering operations is also
improved. Many new and old plants are installing digesters for the same reasons
despite their apparent cost burden. The
digester does provide the utility with the ability to eliminate all sludge
disposal with the addition of new technologies which monitor and control the
aerobic and anoxic zones in the digester.
ENGINEERING
COSTS
Total
engineering costs are listed as $433,200 for the original project. The breakdown of this cost is as follows:
Facility
Plan $ 15,000
Effluent
line design $108,000
Blowers/Digester
design $ 85,200
Bid/constr.
Svcs. $225,000
TOTAL
ENGINEERING $433,200
However,
with the revised scope the effluent line has been eliminated. Consequently, a reduction in
bid/construction services has been deducted from the original estimate. The new total costs are as follows:
Facility
Plan $ 15,000
Effluent
line design $108,000
Blowers/Digester
design $ 85,200
Bid/constr.
Svcs. $157,000
TOTAL
ENGINEERING $365,200
Based
on a total current project cost and accounting for the lost cost due to the deletion
of the effluent line which was already paid for by the City, the cost of total
engineering as a percentage of construction cost is 17.6%. This cost is higher than the cost normally
anticipated of 11-13% for this type of project but is not unacceptably high.
DISCUSSION
The
current plant is under a WVDEP notification of its intent to sue to improve its
operations and is facing civil penalties for past discharge violations. The plant is generally producing an effluent
with average pollutant concentrations less than its permitted average but has
had significant excursions above its maximum permitted levels. The plant
operators are unsure of the cause of most excursions but acknowledge that cold
weather filamentous bacteria outbreaks in the SBR basins contributed to several
of the plant violations of the discharge permit. In addition, a foreign substance has entered the basins on
several occasions which killed a majority of the bacteria necessary for treatment
of the influent BOD materials. The plant
is also approaching its design capacity of 1.2 million gallons per day
(MGD). The WVDEP has allowed the plant
an additional 150,000 gallons per day above its yearly 1.05MGD average as of
February 2004. Since that time nearly
35,000 gallons per day of that capacity has been consumed. The addition of the
blowers may allow a permitted capacity increase if a review supports the City's
engineering calculations and initial operation verifies the improvement in
effluent quality.
The
City of Charles Town has been hampered in its efforts to expand sewage capacity
by several unrelated issues. There has
been a significant resistance by some concerned citizens to what has been
perceived to be poorly regulated growth in the County, objection to the
construction of new facilities by partners to the City's Sewage Service
Agreement, and finally, by a changing regulatory environment. The eastern panhandle of the State and other
eastern bay watershed areas are also affected by the pending regulations which
are designed to provide protection to the Chesapeake Bay, which has been
seriously impacted by nutrient pollution.
In 1998 the City expanded sewage plant capacity to meet the needs of
home buyers desiring to escape the congestion of the Washington D.C.,
metropolitan area. As a result of the
rapid growth occurring in the County, the capacity added in the plant expansion
project was rapidly consumed. The lack
of capacity led to the WV Bureau for Public Health and the WVDEP to halt
approval of building permits in late 2003 implementing an unofficial moratorium
on sewer availability. Despite these
setbacks, the City undertook an aggressive plan to add plant capacity and
submitted a project in early 2004. The
original plan was later modified to address regulatory issues associated with
the capacity improvement. The previous
project plan submitted included:
$
The addition of two new air blowers to the plant
blower building.
$
The construction of a large sludge digester with
an associated blower building for sludge aeration to assist with sludge
disposal and provide additional sludge wasting for proper maintenance of sludge
levels during normal operation and during storm events. This should also assist with control of
filamentous bacteria during cold weather, high BOD events.
$
The addition of a large effluent line to remove
the effluent from Evitts Run, a small stream adjacent to the plant, to the
larger Shenandoah River.
The
possible capacity increase is due to the additional oxygen available to the SBR
basins. The new blowers would allow a
twofold increase in air supplied to the basins significantly increasing the
amount of biological material which can be treated with a concurrent increase
in treatment capacity of the high strength influent BOD materials which
occasionally enter the plant. This
process improvement was estimated to allow a reduction in the maximum allowable
permit limit for BOD5 content and the maximum ammonia nitrogen
content of the plant effluent than is currently required by the existing NPDES
permit issued by the WVDEP. As a
result, an increase in plant capacity would be
possible without adding additional SBR basin capacity. However, the WVDEP had originally
interpreted stream modeling criteria and pending stream anti-degradation
criteria as requiring that an increase in total plant effluent flow would
require discharge to a larger body of water.
This was believed to be a method to increase plant capacity without any
other plant additions. Hence the
original project filing included only the effluent line to the Shenandoah. However, after a second review of the
pending regulations and anti-degradation requirements for both Evitts Run and
the Shenandoah River, it was determined that the pending regulations would not
allow any additional pollutant concentration to either the stream or the
river. At that point, only improvements
in the quality of plant effluent would be allowed if capacity were to increase. The blowers and the digester were added to
the project and provide the potential for effluent quality improvement and a
potential for sludge reduction. The
additions would allow the WVDEP to reduce the maximum effluent permitted
limits for BOD and ammonia nitrogen by approximately 30%. This will in
effect allow plant permitted hydraulic capacity to increase to a higher
level without impacting the total maximum permitted pollutant discharge
load.
Consequently,
it soon became apparent that the effluent line was, therefore, a useless expenditure
and improvements targeted to maintaining or improving plant effluent quality
would be the only economically viable path to capacity increases. The SBR blowers will maintain or improve
effluent quality while the digester addition allows for more flexible plant
operation and provides a better quality sludge while reducing the amount of
sludge to be disposed of at the land application site. Therefore, the blower addition by itself
will allow a capacity increase and the digester will provide a cost savings as
capacity increases. In addition,
pending Chesapeake Bay protective criteria will require future nutrient
reductions in plant effluent and likely result in the need for effluent
tertiary treatment installations to allow future plant capacity additions. Those additions will also include the
construction of a forth SBR basin and possibly a fifth basin if growth
continues in the County. The investment
saved by the elimination of the effluent line will allow those future
improvements to be installed with only a small rate impact for all customers.
This
project has been reviewed in its various forms several times by Staff. Multiple
visits to the plant were conducted, multiple discussions were held with the
City management, the City's Engineer, the WVDEP, the Intervenor protesting the
project and internally with all Technical and Legal Staff. The City had proposed that the SBR blowers
should be removed from the project and installed immediately as a normal course
of business expense. This position was
taken for a multiple of reasons. These
were and are the following:
$
The City has experienced several past excursions
above its permitted discharge limits and as a result is facing significant
potential civil penalties levied by the WVDEP from a lawsuit filed for those
permit violations for the three years of past violations ending in 2003.
$
The original design BOD5 loading of
400 mg/l was revised in January 2004 after a recalculation of actual plant
performance to 500 mg/l for the existing plant. This loading is surpassed frequently with readings as high as 900
mg/l which contribute to excursions from permitted discharge limits. The additional air will effectively
eliminate discharges above permitted limits due to insufficient air in the SBR
basins during high BOD inflows.
$
The blowers were going to be funded with a
developer contribution at no cost to the City.
$
The blowers will not add capacity unless
the WVDEP approves an increase in capacity as a result of the additional air
available to the basins. The immediate
installation of the blowers can be completed as an important part of the resolution of the WVDEP civil action to
prevent future discharge violations. The blowers can be installed under the
existing permit.
OTHER
ISSUES
During
Staff's frequent visits to the treatment plant and discussions with the
operating manager, Staff noted that it's review indicated that additional
financial and employee resources would be needed to improve both system and
plant maintenance activities once the project was completed. The City has a rate ordinance awaiting final
public comment which will supply additional financial resources to the
utility. Staff anticipates several
improvements in maintenance once the funds are available, particularly in the
evaluation and identification of Inflow and Infiltration (I&I) sources and
the scheduling of maintenance and repair activities.
There
has been significant public protest for this project. Much of the protest was related to allowing a discharge directly
to the Shennandoah River, via the now deleted effluent line. Other protest issues centered on the past
performance of the plant related to violations of its discharge limits and
pending civil action by the WVDEP. The
protestants had particular interest in the bacterial discharges from the plant
and the detrimental health effects that it created for swimmers in the
Shennandoah River. The plant has
significantly improved its ultra-violet (UV) disinfection system maintenance
which has significantly reduced that problem and the plant has been in
compliance with its permit for over 18 months with only one excursion. Concerns were also noted by the opponents of
the project that the methods of testing for pollutants in the plant discharge
may be inadequate. Testing requirements
are set by the WVDEP and no violations of those procedures have been noted. Staff does believe that it would be in the
City's best interest to add to the existing test requirements on a temporary
basis to confirm plant operations under all operating conditions as a means to
isolate and correct any problems it may be unaware exist.
In
the Jefferson County area and the Eastern Panhandle of West Virginia in
general, there is a likelihood of sinkholes developing in the fractured karst
topography at any time. The opponents
of the project are concerned that while I&I sources are certainly a problem
affecting plant performance, the loss of sewer flows through broken pipe
joints, poorly made pipe taps and failed pipes due to ground movements are a
danger to groundwater. The plant records indicate that I&I for the entire
systems served by the Charles Town plant is lower than in most other systems of
similar age. Consequently, the concern
that reverse I&I is actually occurring.
Staff is of the opinion that the increased maintenance activities,
particularly video line inspection will resolve that issue and would encourage
the City to include that in a revised maintenance plan.
Many
of the protest letters addressed the cost and quality of life impact of
unregulated growth within the County.
The letters of protest encouraged the Public Service Commission to take
a broad view of the impact of this proposed project on the entire State and
County cost structures. Those issues
raised by the opponents of the project were not a consideration in Engineering
Staff's recommendations.
The
City also filed with the Certificate, an Amendment to a Sewer Service Agreement
between the three utilities receiving service from the Charles Town plant,
Charles Town, Ranson and the Jefferson County Public Service District. The Amendment defines the financial
responsibility for the project financing by each party and provides an
allocation of capacity with that financial commitment. The Amendment was an issue at a hearing to
resolve a moratorium issue for the parties to the original Agreement in Case
No.04-0682-PW-PC. Staff opposes the
terms of the Amendment which calls for capacity reservation but acknowledges
that the utilities have been sharing financially to the operation of the
Charles Town plant since 1988. There is
currently no resale rate established in the City of Charles Town's sewer tariff
and none adopted in its most recent rate ordinance. Staff believes this Agreement severely limits the ability of the
Charles Town Sanitary Board to fulfill its responsibilities as a sewer utility
to provide service due to the need for approval from other utilities to make
investments in its plant and to meet the requirements of the various regulatory
agencies. Since the Agreement has been
in effect since 1988, Staff acknowledges its importance in moving forward with
this project and will recommend it be accepted on a temporary basis with
conditions. Furthermore, Staff opposes
the provision of the Agreement which reserves capacity and believes it should
be stricken to allow customers to be served on a first come first serve basis. In addition, Charles Town must establish a
resale rate for sewer service within 120 days, otherwise, Staff will petition
the Commission for a General Investigation to establish a resale rate for the
City of Charles Town. This will
eliminate the need for the current Agreement.
FINANCIAL
REVIEW
On
January 26, 2004, the City of Charles Town Sewer Department filed an
application for a Certificate of Convenience and Necessity to construct a new
sewer effluent line to discharge into the Shenandoah River. The City of Charles Town submitted a Rule 42
exhibit, Form 4 and Form 14 with this application. The total estimated project costs were $3,200,000. The City of Charles Town planned to finance
this project by issuing revenue bonds
in the amount of $3,200,000. The City
of Charles Town submitted a confirmation letter from Crews and Associates
concerning the issuing of the $3,200,000 in revenue bonds. Crews and Associates is acting as
underwriter for the issuance of the revenue bonds. The terms of the $3,200,000 are for 30 years at 5.5%. The City of Charles Town is not proposing to
obtain interim financing in this certificate project.
The
City of Charles Town currently treats sewage for the City of Ranson and the
Jefferson County Public Service District (District). The City of Charles Town has also submitted an amendment to the
sewer service agreement between them, the City of Ranson and Jefferson County
Public Service District. Staff prepared
a cash flow statement based on the City of Charles Town's Rule 42 exhibit (See
Exhibit 1). All going level adjustments
for revenue, operation and maintenance expenses, and debt service payments are
based on the City of Charles Town's purchase of Tuscawilla sewer operations. The City of Charles Town purchased
Tuscawilla on December 31, 2002, and therefore, only 6 months of revenue and
expenses are recorded at per books. The
going level adjustments are to annualize these numbers. The pro forma adjustment to revenue is based
on the City of Charles Town receiving payments from Huntfield, L.C. The debt service payment associated with
this proposed loan will be initially made by a land developer named Huntfield,
L.C., which is a Virginia limited liability company. The City of Charles Town submitted a letter of credit from
M&T Mortgage Corporation for Huntfield, L.C., in the amount of
$1,700,000. The City of Charles Town
informed Staff that this letter of credit is renewable on an annual basis
between M&T Mortgage Corporation and Huntfield, L.C. The City of Charles Town is relying on receiving
future payments from the City of Ranson and Jefferson County Public Service
District in order to continue making these debt service payments. The City of Charles Town's water department
will also be providing $33,683 of annual revenue to the sewer department. The City of Charles Town's water and sewer
operations are defined as a combined utility under the WV State Code.
The
City of Charles Town is not proposing to raise rates to pay for this proposed
certificate project. Staff has attached
a copy of the City of Charles Town's current rates (See Exhibit 2). The City of Charles Town is planning to pay
for this project with nontraditional certificate project funding.
On
May 26, 2004, the City of Charles Town filed an amendment to this certificate
case. The amendment increased the total
estimated project costs from $3,200,000 to approximately $6,000,000. The increase in estimated project costs was
for the new sewer effluent line to discharge into the Shenandoah River, adding
a sewer digester, and 2 new blowers. A
new confirmation letter from Crews and Associates was also submitted for a loan
in the amount of $6,000,000. The terms
of the loan would be for 30 years at 5.5%. The City of Charles Town also
submitted a revised Rule 42 exhibit.
Staff prepared a cash flow statement based on the City of Charles Town's
revised Rule 42 exhibit (See Exhibit 3).
All going level adjustment are the same as contained in the original
Rule 42 exhibit. All pro forma
adjustment have been increased due to the increase in total estimated project
costs. The methodology for the pro
forma adjustments are the same as the previous Rule 42 exhibit.
The
City of Charles Town has submitted an agreement between them and Huntfield,
L.C. Huntfield, L.C., which estimates
that approximately 2,778 new houses will be constructed over the next 13
years. Huntfield currently owns
property within the geographical boundaries of Jefferson County Public Service
District. The estimated 2,778 new
houses will become customers of the District and their sewage would flow to the
City of Charles Town to be treated. As
new houses are built and sewage flows increase, the Huntfield, L.C., debt
service obligation would decrease. The
Huntfield, L.C., obligation to make the debt service payments of the City of
Charles Town's revenue bonds would end when the flows reach 8,100,000 gallons
per month or 270,000 gallons per day which is equivalent to 1,800 new
houses. Staff calculated the 8,100,000
gallons per month by taking 1,800 new houses (1,800 new EDU's) and multiplying
that by 4,500 gallons per month. The
amendment to the sewer service agreement states that an EDU is equivalent to
4,500 gallons per month. Staff's calculation also contains information provided
by the City of Charles Town to Staff containing the estimated new EDU's per
year, principal and interest payments after Capacity Improvement Capital Cost
fees are collected, and required developer subsidy for the proposed loan. Revenue to be collected by the District to
be paid to the City of Charles Town for the proposed debt service are defined
as Equivalent Dwelling Units (EDU's).
EDU's are outlined in section 2.B of the revised sewer service
agreement. An EDU is listed in this
agreement in the amount of $12.34 for all new sewer service customers and is
equal to 4,500 gallons of sewer usage.
Under this sewer service agreement, the City of Ranson and Jefferson
County Public Service District will remit $12.34 per new customer per month to
the City of Charles Town and this money is dedicated solely for make debt
service payments on the $6,000,000 loan.
As the payments from EDU's increase the developer's debt service
payments will decrease. If approved by
the Commission, all Capacity Improvement Capital Cost (CICC) fees to be imposed
on all new sewer users would be used to pay down the principle on the
$6,000,000 loan. The City of Ranson
attempted to pass a municipal rate ordinance including Capacity Improvement
Capital Cost fees. This ordinance was
appealed and is currently pending before the Commission (Case No. 04-1221-S-MA,
City of Ranson). The Commission has not
issued a Final Order in Case No. 03-1490-PSD-T-PC, Jefferson County Public
Service District, approving their request for Capacity Improvement Capital Cost
fees. The City of Charles Town's
current tariff contains a Capacity Improvement Capital Cost fee. Staff notes that the City of Charles Town
does not currently have a resale rate in its sewer tariff. The City of Charles Town bills the City of
Ranson and the Jefferson County Public Service District based on a 1988 sewer
service agreement.
On
August 9, 2004, Staff met with the City of Charles Town and the Department of
Environmental Protection to discuss revising the scope and financing of this
certificate project. The City of
Charles Town proposed revising the total estimated project costs from
approximately $6,000,000 to approximately $500,000. The revision to the scope of this project was for the City of
Charles Town to add only the 2 blowers.
This removed the new sewer effluent line to discharge into the
Shenandoah River and the digester from this certificate project. The City of Charles Town proposed to Staff
that the $500,000 for the 2 blowers is in the normal course of business and
that they wanted Staff to give them an opinion as to this proposal. Huntfield, L.C., offered to write a check to
pay for the 2 blowers. Staff informed
the City of Charles Town that it still qualified as a certificate of
convenience and necessity and would not be considered the normal course of
business. The City of Charles Town
stated that if they were going to have to file for a certificate of convenience
and necessity, they should again include the digester in the project.
On
August 17, 2004, the City of Charles Town submitted a second amendment to this
certificate project. The change in
scope removed the new sewer effluent line to discharge into the Shenandoah
River. The 2 blowers and the digester
would remain in the project. The total
estimated project costs have been revised from approximately $6,000,000 to
$2,500,000. On August 18, 2004, the
City of Charles Town submitted a 2nd revised (3rd actual)
Rule 42 exhibit. Staff prepared a cash
flow statement based on the City of Charles Town's revised Rule 42 exhibit (See
Exhibit 4). The City of Charles Town is
currently in the process of passing a municipal rate ordinance. This ordinance has not yet become final. The City of Charles Town included as part of
the going level revenue adjustment the projected revenues that would result if
municipal rate ordinance passed and was enacted. The pro forma adjustment to revenue is in the amount of $263,300
will be based on the City of Charles Town receiving payments from Huntfield,
L.C. The debt service payment
associated with this proposed loan will be initially made by a land developer
named Huntfield, L.C. The City of
Charles Town is relying on receiving future payments from the City of Ranson
and Jefferson County Public Service District in the order to continue making
these debt service payments. The City
of Ranson and Jefferson County Public Service District would pay the
$203,300. The remaining $60,000 would
also be paid evenly ($30,000 each) by the City of Ranson and Jefferson County
Public Service District for their share of the $90,000 in increase operation
and maintenance expenses. The debt
service expense has been changed in order to reflect payments on the $2,500,000
loan. This revised Rule 42 exhibit did
not include an adjustment to other revenue from the City of Charles Town water
department.
A
hearing was held in this case on August 24, 2004. Staff did not submit a Final Recommendation in this case before
the hearing. This was due to the City
of Charles Town changing the scope and the financing again. Staff received the 3rd revised
Rule 42 exhibit the night before the hearing.
A new commitment letter from Crews and Associates for the revised loan
in the amount of $2,500,000, including revised terms of 20 years instead of 30
years at 5.5% was received on August 27, 2004.
The revised calculations for the $90,000 annual operation and
maintenance adjustment which the Staff Engineer has adjusted to a level of
$104,000 at pro forma included in the 3rd revised Rule 42. The City of Charles Town Water Department's
cash flow statement for the year ending June 30, 2003, shows a cash flow
surplus at pro forma of $106,588, which is sufficient to provide the $61,132 in
other revenue being pledged by the Water Department. The revised amendment to
the 1988 sewer service agreement includes a reduction per EDU from $12.34 to
$6.10. Charles Town's revised application indicates a decrease in the amount of
the irrevocable letter of credit from $1,700,000 to $700,000, the revenue bonds
will be issued in the amount of $2,500,000 instead of $6,000,000. Huntfield, L.C., the City of Charles Town,
the City of Ranson and Jefferson County Public Service District will be bearing
the debt service payments associated with this certificate project.
The
City of Charles Town's pro forma adjustment to operating revenue assumes that
there will be approximately 2,778 new houses constructed over the next 13
years. The City of Charles Town's 3rd
revised Rule 42 exhibit does not take into consideration the worse case
scenario, which is no new houses constructed over the next 13 years. Staff performed a rate impact comparison on
the existing customers of the City of Charles Town, the City of Ranson, and
Jefferson County Public Service District under the worse case scenario analysis
of the total costs associated with this certificate project. Staff used the City of Charles Town's total
debt service payments for the proposed loan through Crew and Associates and the
estimated increase in operation and maintenance expenses. Staff used the number of customers listed in
each of the listed utilities annual reports on file for the year ending June
30, 2003. Staff's analysis shows what
each customers sewer bill per month would need to be increased by each utility
in order to cover costs associated with this certificate project. This analysis shows that Charles Town would
need to increase rates by approximately $5.36 per customer per month, Jefferson
County Public Service District would need to increase rates by approximately
$5.08 per customer per month, and the City of Ranson would need to increase
rates by approximately $6.26 per customer per month. This scenario assumes that Huntfield, L.C., line of credit would
be exhausted in approximately 3.5 years.
The annual debt service payment are proposed to be $203,300 and the
letter of credit is for $700,000.
Staff's calculations are as follows:
Adjusted
Annual Operation and Maintenance expense
and
debt service payments for this certificate $307,300
Allocation
between the 3 sewer utilities ) 3
Annual
Certificate Case Expense per utility $102,433
CHARLES
TOWN
Annual
Certificate Case Expense per utility $102,433
#
of customers per utility
1,519
Additional
cost per customer per year $ 67.43
12
months ) 12
Additional
cost per customer per month $ 5.62
JEFFERSON
COUNTY PSD
Annual
Certificate Case Expense per utility $102,433
#
of customers per utility 1,603
Additional
cost per customer per year $ 63.90
12
months ) 12
Additional
cost per customer per month $ 5.33
RANSON
Annual
Certificate Case Expense per utility $102,433
#
of customers per utility 1,301
Additional
cost per customer per year $ 78.73
12
months ) 12
Additional
cost per customer per month $ 6.56
RECOMMENDATIONS
The project cost has been reduced from its previous
cost with the effluent line of $6,000,000 to a far lesser $2,500,000. Part of
the borrowing is being guaranteed by a large developer with an interest in home
construction.
The
project is convenient as it will improve the discharge effluent quality during
high BOD inflow events and reduce the sludge disposal cost for the
Utility. The project is needed to
support continued growth in both industrial, commercial and residential
construction.
Consequently,
Staff makes the following recommendations;
1.
The
City of Charles Town 2nd
amended application for a Certificate of Convenience and
Necessity should be approved. The
Certificate should be contingent upon the issuance of the WVDEP NPDES permit
establishing the new discharge criteria for the plant and for the installation
of all new plant additions.
2.
The
existing Sewer Service Agreement which the three Utilities have operated under
since that time is in Staff's view an impediment to the ability of Charles Town
to fulfill its obligations under the PSC Rules to provide service when needed
and meet the requirements of all other Regulatory Agencies. The Amendment filed with the application
which stipulates the financial responsibility of each utility with respect to
debt service and Operation and Maintenance costs of the Charles Town plant and
also allocates capacity to each utility should only be accepted on a temporary
basis with the following conditions:
A. The
1st revised Amended Sewer Service Agreement will require all parties
to share any increased costs of the plant and debt service costs equally but no
capacity reservation will be a part of that agreement and all customers will be
served on a first come first serve basis.
B. The City of Charles Town shall establish a
resale rate for sewer service within 120 days.
Failure to establish a resale rate within 120 days will result in Staff
of the Public Service Commission petitioning the Commission for a General
Investigation into the City of Charles Town for the establishment of the
respective resale sewer rate.
C.
The 1st revised Amended
Sewer Service Agreement between the City of Charles Town, the City of Ranson,
and Jefferson County Public Service District be approved for a period of up to
1 year with the exception noted in AA@ above or until the resale rate is
implemented by the City of Charles Town, whichever comes first.
3.
The
City should take action after its pending rate ordinance is adopted to immediately
address the maintenance issues with the new project and to improve the
maintenance activities within its system.
4.
Contingent
upon receipt of the revised letter of credit between M&T Mortgage
Corporation and Huntfield, L.C., in the amount of $700,000.
5.
Approval
of the agreement between the City of Charles Town and Huntfield, L.C.
6.
A
copy of the bids are to be filed with the Commission and made part of the file
as soon as they are tabulated.
7.
If
there is any change in the plans, scope, terms of financing the project, the
City of Charles Town should request a reopening of the Certificate Case for
adjustments and approval.
Finally, Staff
encourages the City of Charles Town to file a Certificate for the Phase II
improvements with the tertiary treatment facilities within the next four months
to alleviate all capacity and discharge water quality concerns for the Charles
Town plant.
JW:RL:vg
Attachments:
Exhibit
1- Cash flow statement based on the City of Charles Town's Rule 42 exhibit
Exhibit
2- The City of Charles Town's current rates.
Exhibit
3 - Cash flow statement based on the City of Charles Town's revised Rule 42 exhibit.
Exhibit
4 - Cash flow statement based on the City of Charles Town's 2nd revised (3rd actual) Rule 42
exhibit.
Exhibit
5 - Cash flow statement based on the City of Charles Town's 3rd revised Rule 42 exhibit the night
before the hearing.