Go to: OVERVIEW (SaveOurCounty)     DETAILS (listener)     PLANNING     SCHOOLS     ENVIRONMENT     EROSION     Report corrections+broken links to Webmaster     Get updates on local issues

 

Division of Water and Waste Management

1560 Kanawha Boulevard East

Charleston, WV 25311

Telephone (304) 558-0641

Fax Number (304) 558-3778

West Virginia Department of Environmental Protection

               Bob Wise                                                                                        Stephanie R. Timmermeyer

               Governor                                                                                         Cabinet Secretary

 

MEMORANDUM

TO:         Mike Johnson, P.E., Assistant Director, DWWM

FROM:  Ed Burdette, PE., DWWM

DATE:   December 12, 2003

SUBJECT: Jefferson Co. PSD — Flowing Springs/Cattail Run Preliminary Engineering Report and Facility Plan

               IJDC Preliminary Application 2003S-774

               Technical Review

 

RECOMMENDATION

 

               The Pre-application, Preliminary Engineering Report and Facilities Planning Report for the Jefferson Co. PSD [Public Service District] — Flowing Springs/Cattail Run Facility Plan has been reviewed. I recommend that the project not be certified to the finding committee at this time.

 

PROJECT DESCRIPTION

 

               The project consists of the construction of approximately 200,300 linear feet of 6, 8, 10, 12, 21 and 24-inch gravity sewers and necessary manholes, 51,600 linear feet of 1½, 4, 6 and 12-inch force mains, 6 duplex grinder pump stations, 5 main pump stations and one 1.0 million gallon/day sequencing batch reactor [SBR] sewage treatment plant [STP] with tertiary filtration. The project is designed to initially serve 2,180 equivalent dwelling units.

 

NEED FOR PROJECT

 

               Customers in the project area are currently served by on site septic tank/soil absorption fields and 11 small package treatment plants. It is documented in the facility plan that septic tank/soil absorption fields are not a viable method of sewage treatment due to unsuitable soil conditions in Jefferson County. As a result of the soil conditions both surface and groundwater are being polluted by improperly treated sewage.

 

OPERATION AND MAINTENANCE

 

               The Jefferson Co. PSD provides adequate operation and maintenance of their sewage collection and treatment system.

 

DEFICIENCIES

 

               Several deficiencies were noted in the Preliminary Engineering Report and the Facilities Planning Report. These deficiencies in the project prohibit the plan being recommended to the funding committee at this time.

 

1.            Why were two separate documents submitted to the IJDC for review, a Facility Plan and Preliminary Engineering Report [PER]? The Facilities Planning document is not the same as the PER. Both contain information that is pertinent to the project. These documents need to be combined into one document for clarity.

 

2.            The selected alternative is set up to divert the flow of approximately 1,254 customers from the Charles Town STP and providing treatment for them at the new Jefferson Co. PSD STP on Cattail Run. To date no revised or amended agreement has been provided revising the current agreement requirements for distributions of flows and relieving Jefferson Co. PSD from sending all their flow to Charles Town up to .4 mgd. The current agreement would not allow any flows to be diverted away from Charles Town. This is a concern for Charles Town and has been restated in a letter to the PSD as recently as November 7, 2003.

 

3.            The report provides no evaluation of use of existing facilities (i.e. Charles Town WWTP [waste water treatment plant]). The report must evaluate expansion of this STP in order to treat at least part of the expected flows and the capacity available in the collection system to transport sewage to the STP. Mapping and schematic diagrams are needed.

 

4.            The mapping provided in Section 2 shows the planning area overlapping the Ranson expansion area and Section 3 seems to indicate that this expansion area would be served eventually at the Cattail Run STP. Is there an agreement with Ranson to this effect? Our current information seems to indicate differently.

 

5.            The section discussing the current situation does not include a discussion on the existing package STP’s in the study area. These facilities need to be discussed as far as their condition and the acceptability of their current effluent discharges (violations). Also, provide some discussion on the condition of each collection system ([inflow/infiltration] I/I, etc). Indicate the number of customers on each system. Also, which of these package plants will be eliminated by the project.

 

6.            Table 2 lists Harpers Ferry PS 2 [pump station number 2] area customers to be connected to the proposed system. Are these existing Harpers Ferry customers? If so an agreement with Harpers Ferry to remove these customers from their system is needed. Also, Willow Springs is listed as having 266 users; the facility plan for this area does not indicate that this number of customers is present.

 

7.            Provide water usage records for residential customers. Based on these records recalculate the users/EDU’s [flow equivalent to flow from one dwelling unit] shown and all rate calculations.

 

8.            Include the current population to be served by the project. Indicate the number of metered/unmetered and residential/nonresidential customers.

 

9.            Include a list of the PSD’s operators and their certifications and a list of existing Permits.

 

10.          Provide location mapping of all developers listed in section.,.

 

11.          The tables included in Section 3 do not seem to include the proposed users “Along Route 27 near Drive Inn” shown on Table 2. Include these users in the appropriate table.

 

12.          Include a column in the tables in Section 3 indicating which of these users will initially be served at the proposed system.

 

13.          The tables in Section 3 list existing and planned EDU’s for the project include residential, commercial and industrial users in this table.

 

14.          Initial flows at the Cattail Run STP do not support an initial plant design of 1.0 mgd. Especially if the 1,254 users currently served at Charles Town are not connected. A more appropriate design may be .3-.5 mgd.

 

15.          Provide the anticipated peak flow for the STP.

 

16.          The report states that the PSD would start with a 1.0 mgd STP and then expand the plant in 1.0 mgd increments. The wasteload allocation was issued for a plant sized at 1.68 mgd why is this? Additional wasteloads must be obtained for 1.0, 2.0 and 3.0 mgd plants.

 

17.          Additional public participation is needed when the plan is finalized.

 

18.          The STP site and line routings chosen were not located in the previous planning documents prepared for the PSD. Due to this fact all environmental clearances must be obtained for the new plan. This includes the WV Division Of Culture and History, Natural Heritage Program, U.S Army Corps of Engineers and the Fish and Wildlife Service. Also, the USDA-NRCS [natural resources conservation service] and the Jefferson Co. Commission needs to be contacted and/or re-contacted with regards to areas of prime farmland and state wide important soil in the project area.

 

19.          A SBR with tertiary filtration was the chosen STP for Alternative 6S wo/EB [without Elk Branch]. During the selection of the treatment plant the need for tertiary filtration was not discussed. Provide adiscussion on the reasons for selecting advanced treatment.

 

20.          Based on the MHI [median household income] for the area the project would not be eligible for a 1/2% loan for 40 yrs from the SRF fund. A 1/2% loan for 30 yrs looks feasible. It should be noted that at this time no SRF [state revolving fund] funds would be available for this project for at least two years.

 

21.          Provide a statement on the availability of lands for the STP, P.S.’s [pump stations] and lines.

 

22.          The report does not appear to contain current data in some instances as noted by the City Of Charles Towns letter of Nov. 7, 2003.

 

23.          Include the calculations used for the 4,000-gal/mo. rate calculation.

 

24.          This office feels that one of the main obstructions for this project to proceed is the $62.24 rate for 4,500 gal/mo or $55.32 for 4,000 gal/mo. All options available need to evaluated to try to lower this rate. One possible option would be to obtain private developer financing for a larger portion of the project costs. Another option may be to participate in the expansion of the Charles Town STP.

 

               Once these comments are addressed and in particular the PER and FP combined into one document additional comments may be forthcoming.

 

PUBLIC SERVICE COMMISSION STAFF TECHNICAL REVIEW

DATE: December 8, 2003

PROJECT SPONSOR: JEFFERSON COUNTY PUBLIC SERVICE DISTRICT

PROJECT SUMMARY:    Construction of a wastewater treatment plant and collection system.

PROPOSED FUNDING:

Aid In Construction from Developers            $ 1,600,000

Special Appropriations Pool            1,000,000

Infrastructure Council Grant            1,000,000

Loan (0.5%, 30 yrs.)          14,000,000

Loan (0.5%, 40 yrs.)          7,578,604

Other Sources                     558,140

Total                     $25,736,744

 

PROPOSED RATES: Current rates are $48.55 per month for 4500 gallons; proposed rates would be an increase of 28.18% to $62.24 per month.

Application Number: 2003 S-774

FINANCIAL: Donald P. Cook

 

1.            The current tariff rate ($48.55 per month for residential customers) is higher than the average rates attributable to 1.0% of the Median Household Income (MIII) of $35.85 per 4500 gallons. The current tariff rates are lower than the average rates attributable to 1.5% of the MHI of $53.78 per 4500 gallons. The current tariff rate ($43.16 per month for residential customers) is higher than the average rates attributable to 1.0% of the MHI of $35.85 per 4000 gallons. The current rates are lower than the average rates attributable to 1.5% of the MHI of $53.78 per 4000 gallons.

 

2.                The Annual Report of the Jefferson County PSD reflects the following outstanding debt:

Lender                  Balance Date of Maturity  Status

2003 Series A      $1,445,000          2025      Current 

2003 Series B      $85,000                2025      Current

2000 Series A      $1,097,139          2031      Current 

l999SeriesA         $337,371             2030      Current 

1998 Series A      $2,250,000          2028      Current 

1998 Series B      $479,265             2019      Current 

1998 Series C      $662,039             2038      Current 

1993 Series A      $509,756             2013      Current 

1988 Series A      $1,703,069          2028      Current 

1988 Series B      $283,846             2028      Current 

WVHDF Note      $722,759             2008      Current 

WDA Note           $145,000             2000      Current

 

3. The attached cash flow analysis reflects the District’s position at fiscal year ended June 30, 2003.

 

4. The current rate is sufficient to support the current operations, per the annual report. The proposed rate is not sufficient to support the additional debt.

 

ENGINEERING:             David W. Dove, P.E.

 

1. This project will require a Certificate of Convenience and Necessity from the Public Service Commission. Please reference this preliminary .application number on the PSC’s Form No. 4.

 

2. Customer Density/ Cost Per Customer:

 

The estimated cost of the project is 525,736,744. The estimated miles of pipe is 47.5 miles. The estimated number of new EDU customers is 1081. Therefore,

 

1081 new EDU customers / 47.5 miles = 22.8 customers / mile very low

$25,736,744 / 1081 new EDU customers = $23,808 / customer extremely high

 

However, 1081 is the estimated number of new EDU customers. The District states that there are 2.54 people per occupied housing unit which equals 2.54 users/EDU. This translates into 1081 EDU customers/(2.54 users/EDU) or 426 housing units or billable customers the District is actually estimated to acquire. The customer density and cost per customer then becomes:

 

426 housing units!47.5 miles of pipe = 9.0 customers/mile Unacceptable

$25,736,744! 426 housing units = $60,414 / customer            Unacceptable

 

Both the Customer Density and the Cost Per Customer is unacceptable under this analysis.

 

It should be noted that the 1254 existing District customers were not used in these calculations in light of the fact that the District is currently under a binding 1988 agreement with Charles Town for sewage treatment for its existing customers. In Section J of the Flowing Springs! Cattail Run Facility Plan prepared by the District and included in this application, the agreement states in part that, “In the event that the plant capacity is reached prior to the full payment of the bonds, the parties hereby agree to enter into a new agreement for expansion of the plant to the mutual benefit of all parties.”

 

The District also owes a substantial amount of debt service for previous upgrades to the Charles Town plant and ongoing treatment expenses as part of the sewer service agreement (pg. 14 of preliminary application) with Charles Town. As an additional note, Charles Town has stated in this application that they currently are developing plans to upgrade their facilities. Therefore, sewage treatment for the exiting District customers is apparently contractually obligated to the Charles Town plant for some time to come.

 

Customer density and customer count will be definite issues in a certificate of convenience and necessity application required by the PSC. The certificate case would evaluate the actual number of customers ready to take service immediately upon completion of construction. Given the uncertainty of the District’s flows that would be diverted from Charles Town, the actual customer count in the certificate case would likely be closely evaluated.

 

3.            Project Feasibility:

 

While this project (SBR plant on Cattail Run) appears to be technically feasible, the design has been based on an anticipated accelerated growth rate. However, given the low customer density and high cost per customer, the project does not appear feasible. The project is designed based on an approximate 34% growth rate which has reportedly occurred in the last few years. Historic trends for Jefferson County have documented a growth rate of 1.67 percent increase per year based on the 1980, 1990, and 2000 censuses.

 

All lines have been sized based on projected growth and proposed developments. There is no indication if the proposed developments are built on speculation or under a contract basis only. In areas where housing developments are proposed, the higher of either the proposed number of new EDU’s from development or an applied 34% growth factor has been utilized. As such, the lines may be oversized for some time to come, especially if the growth rate does not sustain at least a 34% growth rate for 20 years. Staff is unaware of any areas in West Virginia that has grown at that rate for 20 years.

 

The proposed initial 1.0 million gallon per day treatment plant is a SBR plant that has been sized for 2180 initial users at 178 (gal./EDU) which equals 388,040 gallons per day. An additional allowance for infiltration of 200 gallons per inch diameter per mile per day has been used which equates to 71,409 gallons per day. This equates to a total of 459,449 gallons per day for an initial flow going to a 1.0 mgd plant. Therefore, the initial SBR plant will have approximately 540,551 gallons per day of excess capacity.

 

The treatment plant will be designed and constructed for expansion in 1.0 million gallon per day increments, which will allow the District to expand the plant as required. Allowances for property acquisition and pre-blasting for treatment basins to handle flows up to 3.0 million gallons per day have been included within this initial phase. The central location of the Cattail Run treatment plant may allow development of collection systems to serve the mountain communities and Elk Branch in the future.

 

This design assumes 2180 initial users. However, page one of the application states that only 1081 new EDU’s are estimated. Staff would assume as such that the District is proposing to divert a substantial amount of flow (more than 50% of the District’s current customers) from the Charles Town plant to the District’s proposed SBR plant immediately after construction.

 

Staff again points out that there is no written documentation in this application that Charles Town has agreed to allow that amount of flow to be diverted from its plant. In fact, in section G., Item 5 of the included Facility Plan, a letter dated November 7, 2003, from the City Manager of Charles Town (Jane Arnett) states, that since 1997, the City has provided comments and raised concerns through both correspondence and meetings regarding the District’s Facility Plans. The City once again believes that the concerns brought forth by the Town, to both the District and Pentree, Inc., since 1997, have not been addressed in the current Facility Plan.

 

She further states that the fiscal impact of removing more than 50% of the District’s current customers was not evaluated in the Plan and that Charles Town will continue to raise concerns regarding the redirection of flows of this magnitude in the context of the 1988 Sewer Service Agreement and its EPA 201 study map. Staff would recommend that all the concerns raised by Charles Town be addressed before this project proceeds.

 

It is readily apparent that the issue of diverting the District’s flow from the Charles Town plant to the District’s proposed SBR plant is critical to the feasibility of the District’s proposal at this time. No analysis was presented as to how many of the District’s customers would be required to stay at the Charles Town plant to cover the debt service to Charles Town. As such, the District’s proposed plant and facilities appear to be drastically over designed especially if the District’s flow to Charles Town is not diverted to the District’s proposed new plant.

 

Staff would recommend that the utilities involved renegotiate the agreement for sewer service, to the satisfaction of all the parties and include the revised agreement in this application. The revised agreement would require prior Public Service Commission approval. Unless the District is able to divert its flows from Charles Town, Staff believes the District’s proposed facilities are too large and not feasible due in large part to an inadequate customer base and what will likely be inadequate flows.

 

The District, under the Sewer Service Agreement, has an allowed 400,000 gallon per day capacity at the Charles Town plant. The Town of Ranson has expressed an interest in increasing its allotted sewage flow capacity to the Charles Town plant or possibly building its own treatment plant. The Charles Town plant is at or near its capacity now and will likely need to be upgraded in the very near future if it is to continue to treat sewage from the District, Ranson and itself.

 

The District should explore negotiations with Ranson and Charles Town to possibly sell the District’s capacity at the Charles Town plant. The negotiations should include compensation to the District for any investment in the Charles Town plant from previous upgrades the District has helped to fund. This would appear to be advantageous to all the utilities involved and could assist the District in the plans to build its own treatment plant. If the utilities are unable to negotiate an agreement, the PSC may be petitioned by the utilities, to revise the agreement in the best interest of the public. Without cooperation from all the utilities involved, no projects may be feasible for any of the utilities at this time.

 

4.            Alternatives to Project:

 

The District’s Facility Plan considers 21 alternatives for providing sewage service for specific areas of the Flowing Springs, Cattail Run and Elk Branch drainage areas of Jefferson County. Most of the alternatives consisted of some variation of a centralized wastewater treatment plant located at different locations within the District’s boundaries, with different collection piping arrangements to accommodate that particular design. The problems with these types of systems are high costs ($20,000 - $30,000 per customer), expensive network of collection pipes and failures that can result in large volumes of raw sewage discharged at one point source. These type systems are usually designed for heavily populated areas with high densities and limited space available.

 

At the present time in the District’s boundaries, there is plenty of space available for alternative systems and only clusters of areas with moderate densities. This is evidenced by the nearly 50 miles of collection piping and the low customer density proposed by this application. Of the alternatives considered by the District, a SBR plant may be the better option. At this time, Staff would not agree with the chosen alternative of a SBR sewage treatment plant located on Cattail Run. Without sufficient and substantiated customer base, the proposed SBR plant would likely be cost prohibitive and risky business for the District at this time. Especially, if the accelerated population growth (from 1.67% to 34%) is not sustained for 20 years and given that the District already has one of the highest rates for sewage treatment in the state. Even if the District was to realize half of its 34% projected customer growth for the first few years, the effects could be devastating to the District and an average sewer bill could escalate drastically in order to pay for an oversized sewage treatment plant and collection system.

 

Additionally, Staff found no estimated effluent quality was given for the different types of alternatives considered. Staff would surmise that, before choosing a particular type of treatment plant, the quality of the effluent to be expected from the plant once it is operational should be known, especially since the discharges would be into the Shenandoah River and the area is known for its parks and tourism.

 

Failed septic tanks are often used as a justification for a centralized treatment facility. However, in numerous letters from the Jefferson County Health Department in section J of the Facility Plan, the Health Department states that it is undisputed that Jefferson County has the least percentage of failing systems in West Virginia (less than 2%) and that properly constructed and located septic systems are not a factor in well contamination. This apparent contradiction with the District’s position would be an issue in the certificate case.

 

Additionally, the District should have evaluated in their alternatives:

 

1. The Charles Town treatment plant being upgraded to handle all flows from the District and Ranson, with no plant being constructed by the District or Ranson.

 

2. An alternative for Charles Town and/or Ranson to buy the District’s allotted capacity and the District constructing a treatment plant and/or operating decentralized wastewater treatment systems until substantial growth occurs.

 

These alternatives, as well as those issues raised by Charles Town, should be addressed in order to select the best alternative.

 

5.            Consolidation:

 

No consolidation will occur as a result of this application. In fact, if this application is approved without mutual agreement from all involved utilities, an unreasonable duplication of facilities could occur, particularly if an accelerated growth of 34% for 20 years is not achieved. The District and Charles Town could have treatment plants with an insufficient number of customers and inadequate flows. In essence, the District could be paying in part for two treatment plants, i.e., Charles Town’s and their own.

 

6.            Inconsistencies:

 

Page 2 of the application states that the total amount requested is $25,736,744. Attachment to Attachment 3 of the application lists the total estimated project cost at $25,731,744.

 

7.            Operation and Maintenance Costs:

 

Operation and maintenance cost estimates were provided; however, no supporting calculations were provided. Two O&M figures seem to be provided, one for $370,495 and another of $539,987. Based upon the District’s current leak adjustment rate of $2.76 per thousand gallons, Staff would estimate at least an additional $350,000 per year for O&M expenses at initial start up of the plant. This figure would be over and above the District’s current O&M expenses. It would appear that the District used the lesser of the two figures to estimate rates. If the O&M costs are underestimated, rates would be increased even further. Operation and maintenance cost estimates would at best be a guess without a detailed breakdown and supporting calculations. Accurate O&M cost estimates would be crucial in this case especially since the District already has one of the highest rates in the state for sewage treatment.

 

8.            Engineering Agreement:

 

The District is rated as a class A utility based on annual revenue. As such, the District is no longer required to seek PSC approval of the agreement. The District states however that the engineering agreement has been previously approved by the PSC. Staff does note that the total engineering fees for this project are approximately 20% of the construction costs, which Staff considers high. High engineering fees could be an issue in the certificate of convenience and necessity case or subsequent rate cases that would require PSC approval. As such, the District should not proceed with design until funding is acquired.

 

Jefferson County Public Service District Statement of Cash Flow Year Ended June 30, 2003

 

 

Per

Annual Report

YE 6/30/2003

 

As

Proposed

Based on 4500

As

Proposed

Based on 4000

Available Cash:

     Operating Revenues

     Other Income

        Total

 

 

1,196,172

29,379

1,225,551

 

 

2,003,484

44,339

2,047,823

 

 

2,003,484

44,339

2,047,823

 

Cash Requirements:

     Operation and Maintenance Expenses

     Other Taxes

        Total Cash Required Before Debt Service

 

Cash Available for Debt Service

 

 

831,775

18,811

850,586

 

374,965

 

 

1,202,270

18,811

1.221.081

 

826,742

 

 

1,202,270

18,811

1.221.081

 

826,742

 

Debt Service Requirements:

  Existing Debt:

     Principal & Interest

     Reserves

  Proposed Debt:

     Principal

     Interest

        Total Requirements

 

     Revenue (Deficiency) Excess

 

 

 

353,255

 

 

 

 

353,255

 

21,710  

 

 

353,255

 

 

656,132

55,589

1,064,975

 

(238,233)

 

 

353,255

 

 

656,132

55.589

1,064,975

 

(238,233)

     % Debt Service Coverage

106.15%

77.63%

 77.63%